Your boss wants to know how long your project is going to take. Which part of the plan should you share with your boss?Select an answer:the noncritical tasksthe estimated durations of all tasksthe critical paththe total amount of float in the project

Question

Your boss wants to know how long your project is going to take. Which part of the plan should you share with your boss?Select an answer:the noncritical tasksthe estimated durations of all tasksthe critical paththe total amount of float in the project

🧐 Not the exact question you are looking for?Go ask a question

Solution

You should share the critical path with your boss. The critical path includes all tasks that directly affect the project's completion date. If any task on the critical path is delayed, the entire project will be delayed. Therefore, it gives the most accurate estimate of the project's duration.

Similar Questions

Which of the following provides a sequenced plan that estimates the time required to complete project activities and tasks?Project planProject scheduleCommunication planResource plan

As part of the planning process, a PM is estimating duration for a part-time resource’s task. The PM is assigning the team member a 24-hour task. If the team member is working half time, how many calendar days should the PM plan for the task to get completed?Three daysFour daysSix daysEight days

The first step in managing a project is:Group of answer choicesDefining the timeframe of a projectUnderstanding what you are trying to achieve i.e, its purpose.Just starting it - you don't need a plan.Defining the costs of a project

As a project manager in the planning phase, you have created a project schedule and accounted for the total costs. What is the third major planning component you will create?1 pointA team performance chartA work breakdown structureA risk management planA feedback form

As a project manager, you identify tasks to complete in a project. Who will you consult to create an accurate time estimate for each task?1 pointA project manager from a different teamThe sponsors of the projectTeam members working on the tasksThe project’s primary stakeholders