Which of the following does a project manager do after a change request is approved? Updates the communication planImplements a contingency planRe-baselines the budget and scheduleCreates an impact statement

Question

Which of the following does a project manager do after a change request is approved? Updates the communication planImplements a contingency planRe-baselines the budget and scheduleCreates an impact statement

🧐 Not the exact question you are looking for?Go ask a question

Solution

After a change request is approved, a project manager re-baselines the budget and schedule. This is because the approved change may affect the project's cost and timeline, so it's necessary to adjust the budget and schedule accordingly to reflect the new reality of the project.

Similar Questions

Randy, the project manager, completed a change request to seek approval for the change from the project sponsor.Randy's change request should include a(n) ________, which describes the aspects of the project affected by the change (e.g., deliverables).a.)impact statementb.)change descriptionc.)implementation pland.)status report

Which of the following statements best describes the project manager's responsibilities in relation to scope change managementGroup of answer choicesThe project manager is responsible for relaying all change requests to a change control board and informing the customer about the board's decisions.The project manager is responsible for making all final decisions about the disposition of change requests and communicating those decisions to project stakeholders.The project manager is responsible for making sure all the client's change requests are carried out promptly.The project manager is responsible for identifying and documenting potential changes, assessing their impact on the project, providing that assessment to the change control board, documenting the decisions, and communicating them to project stakeholders.

All of the following are the overall steps a project manager follows to manage change on a project, EXCEPT:Identify the change to clarify the scope of the change, determine who is requesting the change, and decide whether to approve, reject, or defer the change request.Implement the change and update the project schedule, budget, and scope as required as well as communicate about the change.Investigate the change to determine impacts, benefits, and the cost.Integrate the change to the schedule and then get stakeholder approval to integrate the cost of change into the budget.

The project management plan may be changed without a change request only under which of the following circumstances? A. The plan has been written by the project manager and no team member input is included B. The plan has been written but not approved by the sponsor C. The sponsor has approved the plan but the project has not yet started D. The plan has been approved by the sponsor but not yet implemented

Which of the following does the project manager provide at the approval meeting? Task chartLessons learnedTransition planCurrent schedule