Which of the following is true in case of merge activityA. An activity with two or more immediate predecessorsB. An activity with one immediate predecessorsC. An activity with no immediate predecessorsa.B onlyb.A and Cc.A onlyd.A B and C

Question

Which of the following is true in case of merge activityA. An activity with two or more immediate predecessorsB. An activity with one immediate predecessorsC. An activity with no immediate predecessorsa.B onlyb.A and Cc.A onlyd.A B and C

🧐 Not the exact question you are looking for?Go ask a question

Solution

The correct answer is c. A only.

In project management, a merge activity is an activity that has two or more immediate predecessors. This means that it cannot start until all of its immediate predecessor activities are completed. Therefore, option A is correct.

Option B is incorrect because an activity with one immediate predecessor is not a merge activity. It is simply an activity that follows another activity.

Option C is also incorrect because an activity with no immediate predecessors is usually the first activity in the project, not a merge activity.

So, the correct answer is c. A only.

This problem has been solved

Similar Questions

The early start of an activity that has only one predecessor is equal to the early finish of that predecessor.Group of answer choicesTrueFalse

You are given the following activity diagram. Which of the following action sequences are possible during one execution of the activity diagram?Select one or more:A → B → CA → C → BA → CA → B

Select the correct answer.Which of these transitional words signal to the reader that there will be an 'addition'?  A. incidentally B. meanwhile C. furthermore D. nevertheless

Suppose two activities A and B, having start and finish time as SA, FA and SB, FB respectively. Both the activities are said to be compatible, under which of the following condition?1 pointSA = FBSA > FBSA >= FB or SB >= FASA >= FB and SB = FA

Create Network Diagram (2.5pts) A. Use Ms Project to draw a network from the following information. ID Predecessor A None B A C B D B E C F C G D E F H G B. What type of activity is each of the following? Choose one of the following: neither burst nor merge, or burst, or merge. Activity A Activity B Activity C Activity D Activity E Activity F Activity G Activity H