Knowee
Questions
Features
Study Tools

Multiple Choice QuestionWhich of the following is true of scheduling resources?Multiple choice question.Scheduling of resources should always be done after a project is complete.Failure to schedule limited resources does not lead to serious problems for a project manager.Scheduling of resources does not help a manager to gauge the impact of unforeseen events such as turnover.The resource-constrained schedule will materialize as a project is implemented if resources  are truly limited.

Question

Multiple Choice QuestionWhich of the following is true of scheduling resources?Multiple choice question.Scheduling of resources should always be done after a project is complete.Failure to schedule limited resources does not lead to serious problems for a project manager.Scheduling of resources does not help a manager to gauge the impact of unforeseen events such as turnover.The resource-constrained schedule will materialize as a project is implemented if resources  are truly limited.

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

The correct answer is: "The resource-constrained schedule will materialize as a project is implemented if resources are truly limited."

Here's why:

  1. Scheduling of resources should always be done after a project is complete: This is incorrect. Resource scheduling is an essential part of project planning and should be done before and during the project, not after it's complete.

  2. Failure to schedule limited resources does not lead to serious problems for a project manager: This is also incorrect. Proper resource scheduling is crucial for project success. Failure to do so can lead to delays, cost overruns, and other serious problems.

  3. Scheduling of resources does not help a manager to gauge the impact of unforeseen events such as turnover: This is incorrect. Resource scheduling can help managers anticipate and plan for potential issues, including turnover.

  4. The resource-constrained schedule will materialize as a project is implemented if resources are truly limited: This is correct. If resources are limited, the project schedule will need to adapt to these constraints as the project is implemented. This is known as a resource-constrained schedule.

This problem has been solved

Similar Questions

Multiple Choice QuestionWhich of the following is true of smoothing/leveling resources in a time-constrained project?Multiple choice question.There are no risks in a time-constrained project.Changing the precedence relationship of activitiesLoss of scheduling flexibility

Multiple Choice QuestionWhich statement best describes why resources need to be incorporated into a project precedence network plan?Multiple choice question.Inclusion of resources will allow work packages to be accurately estimated.Project network times cannot become a schedule until resources have been assigned.The inclusion of resources into a project network allows for project priorities to be established.

For resource constrained project, the duration of the project might have to be increased in order to improve resource utilization.Group of answer choicesTrueFalse

You have decided to apply Resource Leveling to a project because of a critically required resource being available only at certain times. Which of the following will likely be true?2 MarksResource Leveling can often cause the original critical path to changResource Leveling will over-allocate resources to schedule the p before the deadline.Resource Leveling will require additional resources to complet project.Resource Leveling will never alter the original critical path.

Multiple Choice QuestionThe priority rules for resource smoothing are applied in ___.Multiple choice question.any period when two or more activities require the same resourceany period when a critical path activity is scheduledevery time period of a project

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.