You have decided to apply Resource Leveling to a project because of a critically required resource being available only at certain times. Which of the following will likely be true?2 MarksResource Leveling can often cause the original critical path to changResource Leveling will over-allocate resources to schedule the p before the deadline.Resource Leveling will require additional resources to complet project.Resource Leveling will never alter the original critical path.
Question
You have decided to apply Resource Leveling to a project because of a critically required resource being available only at certain times. Which of the following will likely be true?2 MarksResource Leveling can often cause the original critical path to changResource Leveling will over-allocate resources to schedule the p before the deadline.Resource Leveling will require additional resources to complet project.Resource Leveling will never alter the original critical path.
Solution
The correct answer is: "Resource Leveling can often cause the original critical path to change."
Here's why:
-
Resource leveling is a technique in project management that involves smoothing out the resource usage in a project to minimize the fluctuation of resource allocation.
-
When a resource is only available at certain times, resource leveling can be used to adjust the project schedule to accommodate this constraint.
-
This adjustment often involves changing the sequence or timing of tasks, which can result in a change to the original critical path.
-
The critical path is the sequence of tasks that must be completed on time for the project to finish on the scheduled completion date. Any delay in the tasks on the critical path would delay the completion of the whole project.
-
Therefore, when resource leveling is applied and tasks are rescheduled to accommodate resource availability, it can often cause the original critical path to change.
The other options are not typically true. Resource leveling does not necessarily over-allocate resources or require additional resources. It is about optimizing the use of available resources. And as explained, resource leveling can indeed alter the original critical path.
Similar Questions
Resource levelling attempts to?a.Ensure that the budget abnormalities are overcome.b.Increase the amount of the project manager's authority so that budget dollars can be appropriated.c.Reduce the amount of resources so that they can be shared with on other endeavours.d.Reduce resource requirements by smoothing out period-to period resource assignments.
Multiple Choice QuestionWhy can the traditional critical path, which is based upon precedence logic, be rendered meaningless after resource constrained leveling is used?Multiple choice question.Leveling will impact activity duration as well as sequence.It can't, the critical path is the critical path by definition.Resource availability becomes an over-riding factor to technical precedence.
What is resource leveling in project management
Multiple Choice QuestionWhich of the following is true of scheduling resources?Multiple choice question.Scheduling of resources should always be done after a project is complete.Failure to schedule limited resources does not lead to serious problems for a project manager.Scheduling of resources does not help a manager to gauge the impact of unforeseen events such as turnover.The resource-constrained schedule will materialize as a project is implemented if resources are truly limited.
New critical path/paths might arise due to resource levelling .Group of answer choicesTrueFalse
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.