If a man can complete a task in 5 days on his own but can finish it in 3 days with his son’s assistance, how long would it take for his son to complete the task independently?
Question
If a man can complete a task in 5 days on his own but can finish it in 3 days with his son’s assistance, how long would it take for his son to complete the task independently?
Solution
Step 1: Identify what the problem is asking for. In this case, we want to find out how long it would take for the son to complete the task independently.
Step 2: Identify what information we have. We know that the man can complete the task in 5 days on his own, and that together with his son, they can complete the task in 3 days.
Step 3: Use the concept of work rate, which is the reciprocal of the time it takes to complete a task. The man's work rate is 1/5 (task/day) and the combined work rate of the man and his son is 1/3 (task/day).
Step 4: Subtract the man's work rate from the combined work rate to find the son's work rate. So, 1/3 - 1/5 = 2/15 (task/day).
Step 5: To find out how long it would take for the son to complete the task independently, take the reciprocal of the son's work rate. So, 15/2 = 7.5 days.
Therefore, it would take the son 7.5 days to complete the task independently.
Similar Questions
3 boys can complete a work in 17 days. 1 boy can complete it in: Ops: A. 50 days B. 51 days C. 49 days D. 53 days
If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:4 days5 days6 days7 days
A father can do a job as fast as his two sons working together. If one son does the job in 3 hours and the other in 6 hours,the number of hours taken by the father,to do the job alone is?Options1342
A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days. A alone will take to finish the job is
A, B and C can do a piece of work in 30 days, 45 days and 90 days, respectively. A starts the work and he is assisted by B and C together on every third day. In how many days will the work be completed?Options23243022