Resource levelling attempts to?a.Ensure that the budget abnormalities are overcome.b.Increase the amount of the project manager's authority so that budget dollars can be appropriated.c.Reduce the amount of resources so that they can be shared with on other endeavours.d.Reduce resource requirements by smoothing out period-to period resource assignments.

Question

Resource levelling attempts to?a.Ensure that the budget abnormalities are overcome.b.Increase the amount of the project manager's authority so that budget dollars can be appropriated.c.Reduce the amount of resources so that they can be shared with on other endeavours.d.Reduce resource requirements by smoothing out period-to period resource assignments.

🧐 Not the exact question you are looking for?Go ask a question

Solution

Resource levelling is a technique in project management that is used to examine unbalanced use of resources (usually people or equipment) over time, and for resolving over-allocations or conflicts.

So, the correct answer is:

d. Reduce resource requirements by smoothing out period-to period resource assignments.

This is because the main goal of resource leveling is to balance the demand for resources with the available supply and to smooth out the resource usage rate.

This problem has been solved

Similar Questions

What is resource leveling in project management

You have decided to apply Resource Leveling to a project because of a critically required resource being available only at certain times. Which of the following will likely be true?2 MarksResource Leveling can often cause the original critical path to changResource Leveling will over-allocate resources to schedule the p before the deadline.Resource Leveling will require additional resources to complet project.Resource Leveling will never alter the original critical path.

For resource constrained project, the duration of the project might have to be increased in order to improve resource utilization.Group of answer choicesTrueFalse

As a project manager setting a budget, you factor in unexpected costs that may arise during the project. What budgeting strategy does this refer to?1 pointSetting a baselineBottom-up approachLeveraging expertsAdding a buffer and reserves

What Is Resource Leveling?

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.