In a CPM/PERT network the critical path is the:Group of answer choicesshortest (duration) path through the network.lowest path through the network.highest path through the network.longest (duration) path through the network.

Question

In a CPM/PERT network the critical path is the:Group of answer choicesshortest (duration) path through the network.lowest path through the network.highest path through the network.longest (duration) path through the network.

🧐 Not the exact question you are looking for?Go ask a question

Solution

In a CPM/PERT network, the critical path is the longest (duration) path through the network.

Similar Questions

The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.Group of answer choiceslongest; shortestlongest; longestshortest; shortestshortest; longest

What is the critical path?

The critical pathIs a path that operates from the starting node to the end nodeIs a mixture of all paths.Is the longest pathIs the shortest path

hile solving a network flow problem by PERT, which of the followingtype of time will be used to measure the length of Critical Path? Pessimistic Expected Most Likely Optimistic

Which of the following are some steps to create a critical path? Select all that apply.1 pointMake time estimates.Consult your main customer.Create a network diagram.Set dependencies.

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.