hile solving a network flow problem by PERT, which of the followingtype of time will be used to measure the length of Critical Path? Pessimistic Expected Most Likely Optimistic

Question

hile solving a network flow problem by PERT, which of the followingtype of time will be used to measure the length of Critical Path? Pessimistic Expected Most Likely Optimistic

🧐 Not the exact question you are looking for?Go ask a question

Solution

The length of the Critical Path in a network flow problem solved by PERT (Program Evaluation and Review Technique) is typically measured using the Expected time.

Here's a step-by-step explanation:

  1. PERT is a statistical tool used in project management, which was designed to analyze and represent the tasks involved in completing a given project.

  2. It involves three time estimates to accomplish a task: Optimistic time (O), Most Likely time (M), and Pessimistic time (P).

  3. The Expected time (E) is a weighted average of these three estimates and is calculated as follows: E = (O + 4M + P) / 6.

  4. The Critical Path is the sequence of tasks that add up to the longest overall duration. This path must be completed on time for the project to finish on schedule.

  5. Therefore, the Expected time is used to measure the length of the Critical Path because it provides a realistic time frame, taking into account the most likely completion time and potential delays (pessimistic time).

This problem has been solved

Similar Questions

Time used in PERT for drawing the Network diagram is a.Optimistic timeb.Pessimistic timec.Most likely timed.Expected Time

PERT is use full when we have following time duration except:a.Optimistic timeb.Pessimistic timec.Most likely timed.Certain Duration

A CPM/PERT project network with probabilistic activity times includes an activity with a most likely time of 18 days, an optimistic time of 5 days, and a pessimistic time of 23 days. The mean time for this activity is  (round to the nearest whole number)

In a CPM/PERT network the critical path is the:Group of answer choicesshortest (duration) path through the network.lowest path through the network.highest path through the network.longest (duration) path through the network.

PERT is a three time estimate and gives more weightage toQuestion 3Answera.Optimistic timeb.Most likely timec.Pessimistic timed.Expected time