A and B together can finish a work in 6.75 days. A alone can finish the same work in 9 days. In how many days will B alone finish the work?Options18 days27 days35 days36 days

Question

A and B together can finish a work in 6.75 days. A alone can finish the same work in 9 days. In how many days will B alone finish the work?Options18 days27 days35 days36 days

🧐 Not the exact question you are looking for?Go ask a question

Solution

To solve this problem, we first need to find out how much work A and B can do together in one day, and how much work A can do alone in one day.

  1. A and B together can finish the work in 6.75 days. So, the amount of work they can do in one day is 1/6.75.

  2. A alone can finish the work in 9 days. So, the amount of work A can do in one day is 1/9.

Now, to find out how much work B can do in one day, we subtract the work done by A from the work done by A and B together.

So, the amount of work B can do in one day is (1/6.75) - (1/9).

To find out how many days B will take to finish the work alone, we take the reciprocal of the work B can do in one day.

Let's calculate:

Work done by A and B together in one day = 1/6.75 = 0.1481 (approx) Work done by A alone in one day = 1/9 = 0.1111 (approx) Work done by B alone in one day = 0.1481 - 0.1111 = 0.037 (approx)

So, B will take 1/0.037 = 27 days (approx) to finish the work alone.

Therefore, the answer is 27 days.

This problem has been solved

Similar Questions

A started a work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone finish the whole work?Options2.5 days, 7.5 days5 days, 15 daysNone of these5 days, 8.5 days

A started a work and left working after 9 days now B finished the remaining work in 24 days. Had A left the work after working for 13 days then B would have finished the remaining work in next 18 days. Then find in how many days A and B together can complete the work?Options12 days16 days18 days15 days

A and B together can complete a piece of work in 35 days, while A alone can complete it in 60 days. So, B alone can complete the work in how many days?

Select the correct answerA and B together can finish a work in 5 days. If A works twice his efficiency they can finish the same work in 3 days. In how many days will A alone finish the work?Options5.4 days7.5 days6.6 days15 days

A can do a piece of work in 8 days and B can do the same work in 10 days. They started the work together but after 3 days, A left . In how many days B can complete the remaining work?4 days7 days7.5 days3. 25 days

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.