If the most pessimistic and most optimistic estimates of the amount of time needed to complete an activity are 10 days and 4 days, respectively, the activity's variation is expected to bea.1b.2c.3d.4
Question
If the most pessimistic and most optimistic estimates of the amount of time needed to complete an activity are 10 days and 4 days, respectively, the activity's variation is expected to bea.1b.2c.3d.4
Solution
To calculate the activity's variation, we need to find the difference between the most optimistic and most pessimistic estimates.
Step 1: Subtract the most pessimistic estimate from the most optimistic estimate. 4 days - 10 days = -6 days
Step 2: Take the absolute value of the result to remove the negative sign. |-6 days| = 6 days
Therefore, the activity's variation is 6 days.
Since none of the given options match the calculated variation, the correct answer is not provided.
Similar Questions
A CPM/PERT project network with probabilistic activity times includes an activity with a most likely time of 11 days, an optimistic time of 9 days, and a pessimistic time of 22 days. The variance of the activity in the problem above is (round your answer to 1 decimal place)
A PERT/CPM activity has an optimistic time estimate of 5 days, a most likely time estimate of 10 days, and a pessimistic time estimate of 24 days. What is the expected time (in days) of this activity?Round answer to two decimal places.hint: formula is available in lecture notes
How many minutes do you think you spend on physical activity each day
The activity of a radioactive material is 2.56 × 10–3 Ci. If the half life of the material is 5 days, after how many days the activity will become 2 × 10–5 Ci
A is thrice as efficient as B and takes 10 days less than B takes to do the same work. In howmany days, B alone can finish the whole work?
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.