Imagine that a restaurant supplier has been asked to develop a new dessert for their client, a popular restaurant chain. Even though they are not contractually required to do so, the project team from the restaurant supplier decides to get the client to approve the recipe for the dessert before beginning development on it. From the restaurant supplier’s perspective, what two dependencies does this scenario demonstrate? 1 pointInternal dependencyDiscretionary dependencyExternal dependencyMandatory dependency

Question

Imagine that a restaurant supplier has been asked to develop a new dessert for their client, a popular restaurant chain. Even though they are not contractually required to do so, the project team from the restaurant supplier decides to get the client to approve the recipe for the dessert before beginning development on it. From the restaurant supplier’s perspective, what two dependencies does this scenario demonstrate? 1 pointInternal dependencyDiscretionary dependencyExternal dependencyMandatory dependency

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

This scenario demonstrates two types of dependencies from the restaurant supplier's perspective:

  1. Discretionary Dependency: This is because the restaurant supplier's team is not contractually obligated to get the client's approval on the new dessert recipe before starting its development. They choose to do this as a matter of choice or preference, hence it's a discretionary dependency.

  2. External Dependency: The approval of the recipe from the client is an event or task outside the project team (restaurant supplier) that must occur before they can proceed with the development of the dessert. This makes it an external dependency.

This problem has been solved

Similar Questions

Continuing with the app-development project scenario from the previous question, which three of the following task relationships demonstrate an internal dependency?1 pointDesigners must complete wireframes before they begin prototyping. Developers must fix bugs before the Quality Assurance team begins testing. Clients must sign off on the design before the official launch.Researchers must conduct usability tests before the team can improve the design.Partner agencies must deliver image assets before the app is complete.4.Question 4

Continuing with the construction project scenario from the previous question, the project team completes the designs (Task A) and then begins construction (Task B). What type of dependency describes the relationship between Tasks A and B?1 pointStart-to-Start (SS)Start-to-Finish (SF)Finish-to-Finish (FF)Finish-to-Start (FS)

What steps help project managers manage dependencies? Select all that apply.1 pointRecord dependenciesProper identificationGroup dependencies by costCompare dependencies with competitorsEfficient communicationContinuous monitoring and control

case study on dependency theory

A demolition team needs permits from the city before they can begin work. What type of dependency is this? 1 pointExternal dependencyDiscretionary dependencyPriority dependencyInternal dependency