A demolition team needs permits from the city before they can begin work. What type of dependency is this? 1 pointExternal dependencyDiscretionary dependencyPriority dependencyInternal dependency

Question

A demolition team needs permits from the city before they can begin work. What type of dependency is this? 1 pointExternal dependencyDiscretionary dependencyPriority dependencyInternal dependency

🧐 Not the exact question you are looking for?Go ask a question

Solution

This is an example of an External Dependency. External dependencies involve relying on entities, teams, or individuals outside of the project team to deliver a component or input, or to complete an activity or task. In this case, the demolition team is dependent on the city to provide the necessary permits before they can begin work.

Similar Questions

Continuing with the construction project scenario from the previous question, the project team completes the designs (Task A) and then begins construction (Task B). What type of dependency describes the relationship between Tasks A and B?1 pointStart-to-Start (SS)Start-to-Finish (SF)Finish-to-Finish (FF)Finish-to-Start (FS)

Imagine that a restaurant supplier has been asked to develop a new dessert for their client, a popular restaurant chain. Even though they are not contractually required to do so, the project team from the restaurant supplier decides to get the client to approve the recipe for the dessert before beginning development on it. From the restaurant supplier’s perspective, what two dependencies does this scenario demonstrate? 1 pointInternal dependencyDiscretionary dependencyExternal dependencyMandatory dependency

Identify and describe the four types of dependencies, or relationships, between activities.

In an industrial project the equipment installation can be started 15 days after the equipment foundation is completed. What type of dependency is this?Start-to-finish with a 15-day leadFinish-to-start with a 15-day lagFinish-to-start with a 15-day leadFinish-to-finish with a 15-day lag

nternational projects may be classified into all but one of the following categories. Which one is not one of the typical classificationsa.Strategicb.Political necessityc.Operationald.Compliance and emergency

1/1

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.